Tariff
restructuring and privatisation are key issues facing the
industry
Powering ahead with reforms
Boonsong Kositchotethana
The face of Thailand's electricity
industry has been changing dramatically, spurred by the worst
economic turmoil in recent history, new operating environments
and changing government policies.
Sweeping reforms of the country's power supply industry are underway.
A more definite pattern for deregulation has emerged and efforts
are now geared towards establishing a competitive power market
and setting up a power pool by 2003.
Intensive work has also been undertaken this year to revamp the
country's power tariff structure so that power authorities will
no longer pass on all their costs, some of which arise from their
own inefficiency, to the public.
Taking 1999 as a whole, electricity demand continued to drop
compared to the previous year, though marginally, suggesting that
the economy was still in the doldrums. Power consumption in August
and September showed a slight increase, which was regarded as
a sign of a rebound in the economy.
Sluggish demand and expansion of generating facilities has resulted
in excessive generating capacity in Thailand's system. The surplus
is likely to remain relatively high over the next nine years or
so, in spite of attempts to defer, downsize or even cancel additional
generating capacity.
The recession, the significant slowdown in growth of power demand,
a high level of generating reserve and,
in a few case, public opposition, have prompted a number of changes
in the independent power producer (IPP) projects licensed in Thailand.
The partial sale of the giant state-owned Ratchaburi power station
in Thailand, regarded as a threshold in the reform of the national
power supply industry, has made significant headway. Further good
news at Ratchaburi is that the Mitsui-General Electric alliance
has lived up to its latest promise to complete the long-delayed
construction of the mega power house within the suggested timeframe.
An
additional power station in Laos -- Houay Ho -- started electricity
sales to Thailand on the contracted start-up date -- September
3.
In September, the Thai government acted to avert the short-term
cash flow crisis of the Electricity Generating Authority of Thailand
(Egat) by endorsing its long-awaited plan to borrow 18.12 billion
baht.
Though its critical financial problems were partly resolved,
Egat faced the first loss -- five billion baht -- in its 30-year
history during the fiscal year ending in September. The loss was
primarily due to currency exchanges.
Power industry reforms
A more definite pattern for reforming Thailand's electricity
supply industry is emerging as senior Thai energy planners initially
agreed to adopt the structure proposed by a consulting team led
by Arthur Andersen.
For the time being, the study by the five-company consulting
consortium seems to provide a workable basis for achieving sweeping
reform of the Thai power industry by the target date of 2003.
The recently-completed preliminary study has also offered solutions
to various thorny issues marring the introduction of a competitive
electricity market, Thai officials and industry analysts believe.
For instance, it addresses the subject of stranded costs -- the
unavoidable costs resulting from investment by utilities prior
to the industry restructure.
The proposed structure also drew upon recommendations from Boston
Consulting, which was also retained by Egat, to study the reform.
It is likely that the model proposed by the Arthur Andersen-led
group, which also includes National Economic Research Associates,
Barker, Dunn & Rossi, Cameron McKenna and Presko Shandwick,
will largely be adopted by Thailand, with some modifications.
As part of its assignment, the Arthur Andersen group has yet
to complete a study to define the specific entities to be created
from the existing three state-owned power bodies -- Egat, Metropolitan
Electricity Authority (MEA) and Provincial Electricity Authority
(PEA). The group will come up with a plan and timetable for the
restructuring of these entities.
National Energy Policy Office (Nepo), the de-facto regulatory
body, said the proposed structure of the electricity supply industry
will be submitted to the cabinet for final approval early next
year.
The reforms are aimed at creating a competitive power supply
industry, driving the electricity price down, and improving services
through breaking the monopoly of state power utilities.
Power use drops slightly
Thailand's electricity consumption for the fiscal year ending
in September dropped 0.27% or 214 GWh from the previous year to
80,293 GWh, reflecting the economic doldrums. Peak demand for
the year was on March 18 with record 13,712 MW -- 467.50 MW lower
than the previous year and 574.60 MW below projections based on
the slow economic recovery.
Consumption in the first ten months of the fiscal year showed
a gradual decline. Only in the last two months -- August and September
-- did demand start to rise, spurred by the economic stimulus
package introduced by the government.
Egat said peak demand in September rose 5% over the same period
last year, to 13,507 MW.
With economic recovery apparently on the horizon, the state power
utility said the country's power demand for the new fiscal year
that began in October is expected to grow steadily, both in terms
of generation requirements and peak demand.
For the fiscal year ending in September, the combined power supplied
to Thailand was 90,385 GWh, 2% or 1,749 GWh lower than the previous
year. Egat-operated facilities contributed 76% to the overall
supplies with the remaining 24% purchased from private producers.
Supplies from Egat's own system dropped 7% or 5,380 GWh in the
year to 68,560 GWh while purchases from private producers soared
20% to 3,630 GWh as additional small power producers' power plants
and the Houay Ho hydro power project commenced power sales to
the state power utility.
Average power consumption
(fiscal year 1999)
Metropolitan Eletricity
Authority
Provincial Electircity
Authority
.
Oct-Feb
Mar-Cay
Jun-Sep
Avg. Oct-Sep
Oct-Feb
mar-may
Jun-Sep
Avg. Oct-Sep
Resindence
-12.00
-14.02
-3.72
-9.84
-4.57
-8.68
-2.63
-5.10
Small
business
-10.99
-10.27
-0.43
-7.32
-10.39
-10.57
-3.31
-8.18
Medium business
-4.61
-2.21
-6.83
-0.19
-3.57
-1.72
8.18
0.90
Large business
-8.67
-4.12
1.65
-4.17
-6.69
-1.67
5.41
-1.37
Specialised business
-9.69
-7.03
2.94
-4.93
-7.96
-10.42
4.41
-4.59
Egat's energy sales in the year slipped 1% or 810 MW from the
previous year to 84,584 GWh. The decline was due mainly to the
4% drop in energy sales to the Metropolitan Electricity Authority
(MEA), the power distribution agency for Bangkok and two adjacent
provinces, which took 30,890 GWh.
However, Egat's energy sales to the Provincial Electricity Authority
(PEA), the provincial distribution agency, and direct to customers
as well as Electricite du Laos, increased by 1% from the previous
year.
Big surplus remains
Thailand's excessive generating capacity is likely to remain
relatively high over the next nine years or so in spite of attempts
to defer, downsize or even cancel additional generating capacity.
Based on the present official demand forecast, the minimum oversupply
capacity, termed 'reserve margins' by Thai officials, will begin
to explode to 43.5% in the fiscal year starting in October 1999,
up from 20%.
The reserve margins will climb further to 50% in fiscal year
2001, slowing slightly to 46.6% in 2002, before surging to 52%
in 2003. It will fluctuate but continue on the high side in the
following years.
The reserve margins will not come down to the 25% limit, the
level set by the Thai government, until 2006, according to energy
planning officials.
The significant oversupply in the country's generating capacity
came as a result of planning prior to the mid-1997 economic crisis
which drastically reduced power demand by nearly 10% per annum
compared to the pre-crisis period.
Under the revised load forecast, the average annual peak demand
during 1997-2001 -- the period of Thailand's eighth national plan
-- will increase by 4.02% to 16,214 MW from 13,311 MW, an increase
of 2,903 MW.
Peak power demand growth in 2002-2006 is projected to be 6.46%
a year to 22,168 MW from 16,214 MW, up 5,954 MW. The peak demand
growth will then rise further, by 6.65% a year in 2007-2011 to
30,587 MW from 22,168 MW, an increase of 8,419 MW.
The revised forecast shows a decline in the expected peak in
generation ranging from 9-17% compared to the earlier forecast.
Egat will not be planning any new power plants except for those
already committed. The future additional demand will be served
by power projects implemented by private power producers with
the backdrop of deregulation and privatisation of the electricity
supply industry.
Most of the additional capacity in the national grid will come
from committed independent power producers (IPPs) and power purchases
from neighbouring countries such as Laos.
Under the government's privatisation policy, some of Egat's projects
previously approved by the cabinet will be implemented by IPPs.
Examples are the Ratchaburi thermal units 3-4 and Thap Sakae thermal
units 1-2.
PricewaterhouseCoopers has suggested that the magnitude of Thailand's
reserve margins should be more appropriately reduced to 18% to
be in line with other countries in the region and to reduce Egat's
financial constraints.
New power tariff structure
The government looks set to put in place by the end of 1999 or
early 2000 a revamped electricity tariff structure, which, amongst
other things, will force the state generating utility to assume
more cost risk.
The new structure also envisages tariffs being adjusted to directly
reflect the real costs. Big consumer groups such as commerce and
industries will see their power bills dropping significantly and
residential users will see an increase.
Overall, the new structure, which will be applied during the
fiscal year 2000-2003, will result in a reduction of base electricity
charges by about 2%.
That perhaps summarises Thai authorities' new general approach
to new national power tariffs, derived largely from a comprehensive
study by the London-based PricewaterhouseCoopers.
Though the direction seems clear, there are still at least two
controversial issues under hot debate by the de-facto Thai energy
regulator the National Energy Policy Office (Nepo), government
officials and state power utility executives.
First, whether Egat is allowed to pass on the 95% of costs involved
in the fuel adjustment clause, the so-called Ft in the tariff,
to the public, and assume the 5% risk itself as advised by the
consultant. At present, the entire Ft cost burden is passed on
to consumers.
The second is whether the government should, or more specifically
dare in a political context, follow the PricewaterhouseCoopers
recommendation that the base retail tariff rates now applied to
residential consumers be increased by a substantial amount, as
much as 29% for small users, while cutting the charges for so-called
large general services (LGS) users.
It was proposed that the rate for LGS be trimmed by 11% from
the present level. This group has been paying a higher rate than
the actual power generating costs while small residential users,
using 35 kWh/month, have paid less than cost.
Acknowledging the political sensitivity of the retail tariff
issue, Nepo secretary general Piyasavasti Amranand indicated a
softer approach to adjusting the base retail tariff structure
in the future.
To minimise the social impact on residential users, who would
otherwise have seen an increase in power charges, the government
may allow a small increase in the residential rate and may allow
the tariff for LGS to drop by 4-5% from the present level.
Regarding the PricewaterhouseCoopers' recommendation that Egat
absorb the 5% cost of fuel in the Ft mechanism, Egat deputy governor
for finance Boonchoo Direksathaporn said the matter is a burden
on the state utility. Explaining the logic of its proposal, the
consultant said the recommendation is aimed at motivating Egat
to resort to better fuel management and more efficient fuel utilisation.
Meanwhile, PricewaterhouseCoopers advised that the impact of
the foreign exchange component in the debts should be taken from
the Ft mechanism since this factor has already been part of the
base tariff pricing.
Mr Piyasavasti said Nepo will forward the final recommendation
on the new tariff structure to Savit Bhotiwihok, Minister of the
Prime Minister's Office in charge of energy, and the cabinet for
subsequent approval.
PricewaterhouseCoopers suggested that Egat enhance its generating
efficiency by 5.8% per annum, the Provincial Electricity Authority
(PEA) raise its transmission efficiency by 5.1% a year, and the
Metropolitan Electricity Authority (MEA) boost its distribution
system by 2.8%.