 |
| Commuters
board a BTS skytrain at one of the stations in central Bangkok. |
Despite
the total commitment of the prime minister and transport minister
to bringing long-awaited transport megaprojects such as the new
Bangkok international airport and the capital's first underground
train into service on schedule, clouds of scepticism remain.
The completion
of the new Suvarnabhumi airport by 2005 is widely expected to
be delayed, mainly because of contractual delays and the lengthy
process for choosing contractors.
Contractors
must go through 25 pre-qualification procedures and 27 tender
procedures. All agreements must be approved by the Japan Bank
for International Co-operation, the major creditor.
Delays of
up to one year are being suggested by some industry experts.
A panel
assigned to speed up work on the new international airport at
Nong Ngu Hao has accepted that delays seem inevitable. Work
could not be completed before October 2005, members said.
 |
| ACM
Napporn Chanthawanit (second from right), chairman of NBIA
Co, briefs Prime Minister Thaksin Shinawatra and Pracha
Maleenond, deputy transport minister (third from right)
about features of the new Suvarnabhumi Airport late in September.
|
At least
14 projects are critically behind schedule and this is likely
to affect the whole project. The areas running behind schedule
include the cargo terminal, catering, car parking, water distribution
and waste-water systems, a co-generation power plant, central
utilities and the eastern runway.
The International
Air Transport Association (IATA) and its member airlines have
expressed fears that slow decision-making by executives and
bureaucratic tangles would delay the opening of the airport
to 2007 or beyond.
Even if
it opened on time, the airport would be incomplete and lack
full facilities for the estimated 30 million passengers expected
to pass through it annually, IATA executives warned. If both
the new airport and the existing facility at Don Muang were
to be used, airlines fear a logistical and financial nightmare.
According
to industry data, eight foreign airlines have moved their regional
operational centres away from Bangkok because of worries over
the delays as well as high airport fees and operational costs.
Most relocated
to Singapore, dealing a blow to Bangkok's ambitions to be a
regional aviation hub.
Prime Minister
Thaksin Shinawatra has personally assured that the Suvarnabhumi
airport would be ready to begin operation in mid-2005 with a
capacity to serve up to 40 million passengers annually, up from
the 30 million planners had envisioned earlier.
 |
| A
colourful cake forms the centrepiece at the celebration
of the third anniversary
of the Bangkok Transit System Co skytrain service early
in December.
|
The capacity
could be increased to 40 million per year without the state
having to spend another six billion baht to expand the airport's
passenger terminal, officials now say.
Adjustments
would be made to the terminal's management plan to achieve the
targeted capacity increase and keep alive Bangkok's plan to
become a regional aviation hub, the prime minister said
in response to foreign experts' criticism
of the new airport's limited capacity
and construction delays.
The passenger
terminal, concourse, runways,
aircraft bay and other facilities would
be completed by 2004. Testing would
take about six months, and the project
would be in operation in mid-2005,
Mr Thaksin assured.
The 125-billion-baht
project on the southeastern
outskirts of Bangkok was first
proposed 42 years ago to replace Don
Muang airport in northern Bangkok.But frequent
government changes, allegations
of corruption and the 1997 Asian
financial crisis held up the plan.
Construction on the terminal finally began
in December 2001. The
completion of the new airport is
a key goal of Transport Minister Suriya
Jungrungreangkit, who took office
in October after a cabinet reshuffle.
He also
has expressed considerable enthusiasm
for other efficient mass-transit
systems _ the subway, expressways
and the skytrain.
However,
Prime Minister Thaksin conceded
that a mass transit system would
not be completed in time for the
new airport's opening, but said the
existing expressways and new road links
should be able to initially serve the
airport.
Mr Thaksin,
as chairman of the airport
committee, had asked for a mass
transit tunnel to be incorporated into
the plans for the airport compound, with
advance funding from NBIA.
The tunnel
would serve the yet-to- be-designed
mass transit system. To date,
the government has not decided which
agency should develop this transport option
and bear the cost.
Mr Thaksin
said there would be additional
public works involved in the
airport construction but the overall budget
would not exceed the 100- billion-baht
ceiling.
Delays are
also compromising the opening
date of the city's 20-kilometre underground
railway, linking Hua Lamphong to
the Bang Sue area.
The concession
holder, Bangkok Metro
Co Ltd (BMCL), admitted the operation's
opening will be delayed from
July of 2003 until May 2004 at the earliest.
The holdup
was attributed mainly to
the delay in the signing of the initial agreement
with the Mass Rapid Transit Authority
(MRTA), the state enterprise responsible
for the project.
Some
20 trains had been ordered from
Siemens, the German manufacturer, with
the first one to be delivered in
November of 2003. At least another six
months would be needed for testing of
the system.
The company
insisted the timetable was
in line with the contract that BMCL
had signed with the MRTA, which
owns the 20-km subway project, and
it asked the MRTA to postpone the
start date of the Hua Lamphong- Bang
Sue route, known as the BlueLine,
from July 2003 to August 2004.
Civil works
for the subway project, worth
63.6 billion baht, are 98% complete. However,
the installation of the 17.5-billion-baht
train system, for which BMCL
is responsible, is only 12% complete.Signing was
originally scheduledfor
July 1999, with the service to start in
July 2003. The signing was delayed for
13 months, until Aug 1, 2000, but the
start-up date was left unchanged.
The contract
gave BMCL just 48 months
to complete the project. One
significant reason for the delay is
that BMCL has been unable to solicit sufficient
loans from financial institutions.As well,
the MRTA changed the train
manufacturer, prompting further production
rescheduling.
The fact
that BMCL would be unable to
introduce commercial service in July
2003 has also made it liable to fines
of seven million baht a day.
The
delay is projected to be at least one
year. Accordingly, the consortium could
be liable to pay more than 2.5 billion
baht. A working group is now studying
the legal conditions surrounding the
imposition and collection of the
fine.
Despite
the expected delays, Transport Minister
Suriya still insists that Bangkok's
underground rail system must
be up and running by January 2004,
eight months ahead of the schedule set
by BMCL.
This directive
is aimed at seeing the project
finished as quickly as possible in
order to relieve Bangkok's traffic congestion,
which is starting to increase in
line with fast-rising growth in new vehicle
purchases. In
the middle of November, Mr Suriya
led a delegation to Germany and
Austria to hold talks with top executives
of Siemens over the possibility of
speeding up delivery of the trains
for use in the metro system. It was
hoped they could deliver them before
January 2004.
Siemens
was awarded the 18-billion- baht
contract to supply rolling stock for
the subway. The company also produced
carriages for Bangkok Mass Transit
System Co, the operator of Bangkok's
skytrain system. Though
the opening of the underground train
has yet to occur, the MRTA
is now pressing hard to win government
approval for an extension project,
claiming it will end up deep in debt
unless the subway is extended.
The MRTA
has proposed extending the
Blue Line southward from Hua Lamphong
to Bang Khae, a distance of 13
kilometres.
The
southern extension would cost about
40 billion baht. If approved, work
could start in 2004 and the system could
be ready to serve passengers in 2007.
The National
Economic and Social Development
Board has already approved the
extension project from Hua Lamphong
to Bang Khae. Linking inner Bangkok
with western Thon Buri would ease
traffic congestion in Thon Buri and
around Rattanakosin Island.
The extension
could draw about 190,000
commuters a day, with the original
20-km route drawing 240,000 passengers.
While the
subway extension appears to
be gaining support, the planned extension
of the existing skytrain route has
been stalled. The
Bangkok Metropolitan Authority (BMA)
has yet to come up with firm details
on extensions to the skytrain and
its possible financial participation, while
the Bangkok Mass Transit System Co
(BTSC), the operator, has been struggling
to complete the restructuring of
its 35 billion baht in debts.
Routes from
Onnuj to Samrong (8.9 km),
Saphan Taksin to Taksin Road (2.7
km) and Mor Chit to the Ratchyothin junction
were approved in principle in
January 2002.
According
to the plan, the government and
the BMA would share the cost
of civil works, while BTSC would meet
the cost of tracks and operating the
trains, similar to the investment structure
for the subway project.