Belgians prepare for nuke-free future

Belgians prepare for nuke-free future

Reactors taken offline for repairs

Steam escapes from the cooling towers of the Tihange nuclear power station, one of the two large-scale nuclear power plants in Belgium, on Aug 7, 2018. (Reuters photo)
Steam escapes from the cooling towers of the Tihange nuclear power station, one of the two large-scale nuclear power plants in Belgium, on Aug 7, 2018. (Reuters photo)

BRUSSELS: Belgium's energy production is plunging as its nuclear reactors are taken offline for repairs, with the power shortfall this winter seen as a test of the country's ability to cope when the reactors are phased out from 2022.

Four nuclear reactors at Doel near Antwerp and three at Tihange in Liege, all operated by Electrabel GDF Suez SA, part of France's Engie SA, produce about half of Belgium's electricity when they are fully operational.

Six of the seven -- all built between 1975 and 1985 with an original lifespan of 40 years -- are currently closed for repairs and maintenance, reducing their combined six gigawatts (GW) capacity by nearly two-thirds.

They are expected to come back online between late November and June.

Grid operator Elia System Operator SA has warned it may have to ration electricity during the high-demand winter months, while fears of a supply shortage that could see lights go out and trains stand still have pushed power prices to record highs.

The Doel 1 and 2 reactors were shut down in the spring for repairs to their water-cooling systems, while Tihange 1 went offline on Oct 13 for refuelling and regular maintenance.

Tihange 2 and 3 and Doel 4 are closed while concrete degradation in bunkers close to the reactor buildings is investigated and repaired. Similar concerns led to a shutdown last year at Doel 3, the only reactor scheduled to remain online through November.

"Engie built a new roof for the bunker at Doel 3 and will do the same at the other reactors with concrete degradation,'' deputy director-general Pierre Mongin said.

Belgium's nuclear regulator FANC has said problems in the concrete structures surrounding the four reactors are classed as the lowest level of severity, with no impact on the population or the environment.

This year, Belgium extended the area within which it distributes free iodine tablets for use in a nuclear emergency to all its territory and parts of Germany and the Netherlands, although it said there was no specific risk from the reactors.

John Large, an independent nuclear engineer and analyst, said fixing the concrete degradations could take months longer than Electrabel has projected.

Based on the problems at the other reactors, he said the year-end finish targeted for the repairs at Doel was optimistic, adding: "I would expect them to go into, very certainly into the mid of next year before they can come back online."

Electrabel spokeswoman Anne-Sophie Huge told Reuters the dates given for restarting the reactors -- which will need permission from FANC -- were its best estimate given the information it has.

Elia estimates it will need about 1,700 megawatts (MW) of additional capacity for the winter because of the outages, of which 700-900 MW has yet to be found.

To help make up the loss, Engie has fired up old gas plants and brought in diesel generators, as well as paying heavy industrial consumers to curb their use, Mongin said.

Grilled by lawmakers this month, Engie Electrabel's chief nuclear officer Thierry Saegeman said it would work with Elia to find power but that its first priority was safety.

If shortfalls persist, an eight-stage load-shedding plan devised by Elia could see daily power cuts in rural areas, Danielle Devogelaer of the Federal Planning Bureau told the hearing.

Trains could not operate beyond the first stage of load-shedding, Thomas Baeken, spokesman for rail operator Infrabel, told Reuters -- halting passengers and freight within Belgium, a major transport hub for goods coming from Asia to Europe.

Energy minister Marie Christine Marghem said imported power would help avoid blackouts.

"The month of November, which was critical, is now a lot more secure. For the rest of winter we will continue working," she told Reuters.

A deal to free up capacity on Belgian interconnectors, through which much renewable electricity produced in northern Germany reaches southern Germany, will allow more imports.

Elia CEO Chris Peeters told lawmakers that France would supply 1,000 MW in November and December. Belgium's liquefied natural gas (LNG) imports from overseas are at high levels, with six tankers due to arrive within days.

But Peeters was "less positive" about January and February, especially if a cold winter limits the energy neighbouring countries can export.

France, for example, has issues with energy availability in winter due to safety concerns at its own nuclear reactors.

Many European reactors are reaching the end of their lives and showing defects that ultimately cannot be fixed.

The struggle to meet energy demand this winter has raised questions about how Belgium will cope after its nuclear reactors are decommissioned.

A law passed in 2003 extended the lifetime of the oldest reactors to 2025, with phasing out due to start in 2022.

Energy expert Devogelaer told Reuters Belgium was likely to rely on natural gas, while an Elia spokeswoman said it expected to make up the loss from nuclear with gas and renewables such as solar and wind, plus higher imports.

The grid operator said in 2017 that at least 3.6 GW of new build adjustable (thermal) capacity would be needed to "cope with the shock of the nuclear exit".

Belgium has an LNG terminal and by 2020 will have interconnectors with France, Luxembourg, the Netherlands, Britain and Germany. But it has yet to begin building new gas-fired power plants.

"It would require the construction of between six to eight gas-fired generators in Belgium to replace the nuclear capacity," said Pierre Georges, lead EMEA utilities analyst at S&P Global.

"The problem is that as of today, no one is willing to build a gas power plant without a market design that would make them profitable."

"A Belgian government plan to subsidise investment in gas plants is being reviewed to ensure it meets European Union competition rules,'' Marghem said.

But the clock is ticking.

"Time is up now, so if we have learned anything from this situation, it is that we should not linger on, we should really go ahead with the construction," Devogelaer said. reuters